thx !
-----
wow....the list is actually quite big still.I'm shooting for this summer as the completion/testing date.
Here's what's gotta be done (in semi order) :
-Plumbing rough-in : I need to get all the I/O lines for the coolant 95% done.
-related to the above , the insulation lines need to be done.This includes the entire pump assembly.
-Once the plumbing is done , I can do the final tank sealing.....This includes a full wash/purge......this is 30 days in itself.
-The N2 stystem needs to be plumbed and tested.....
-During all of this , I should be working on actual computer bits installation.....It's happening in paralell....
-----
This list easily breaks down into several thousand operations......